CPEC Westren Route Projects

Hakla D.I Khan Motorway

Project Hakla D.I Khan Motorway
Project Description Salient Features of the Project:
  • On virgin alignment
  • 285 km length. New 4 lane motorway with 100m R.O.W acquired to upgrade it to 6 lanes in future.
Estimated Cost:
  • Construction: Rs.110,208 million
  • Land Acquisition, properties compensation and shifting of utilities: Rs.11,973 million
  • Total: Rs.122,181 million
Executing Company / Sponsors M/o Communications/NHA
Project Progress Update
  • ECNEC approved separate PC-Is for construction and land acquisition on 07.11.2016
  • Construction commenced and Work in Progress
  • Date of Completion Planned: December 2019

D.I Khan (Yarik) –Zhob (N-50)

Project D.I Khan (Yarik) –Zhob (N-50)
Project Description Salient Features of the Project:
  • On existing alignment (section of N-50) with geometric improvements
  • 210 km in length. Improvement / Upgradation of 2 lane existing road to 4 lane. 100m R.O.W will be acquired to upgrade it to 6 lanes in future.
Estimated Cost:
  • Total (Construction plus land acquisition): Rs.76,486 million
Project Progress Update
  • PC-I Approved by ECNEC on 12th April, 2017
  • Land acquisition in Progress
  • Accorded highest priority in 8th JCC

Zhob Quetta (N-50)

Project D.I Khan (Yarik) –Zhob (N-50)
Project Description Salient Features of the Project:
  • On existing alignment (section of N-50) with geometric improvements
  • 331 km in length. Existing 2 lanes are in very good condition. Addition of 2 new lanes for dualization of Existing N-50 to 4 lane. Geometric improvements will be made to the existing alignment to achieve the design speed. 100m R.O.W will be acquired to upgrade it to 6 lanes in future.
Estimated Cost:
  • Construction: Rs.63,601 million
  • Land Acquisition, properties compensation and shifting of utilities: Rs.3,232 million
  • Total: Rs.66,833 million
Project Progress Update

Khuzdar-Quetta– Chaman Section (N-25)

Project

Khuzdar-Quetta– Chaman Section (N-25)

Project Description Upgradation of the existing 2 lanes to 4 lanes.  
Project Progress Update
  • Sorab – Kalat -Quetta section will form part of Western Route
  • Detail designing and feasibility in progress

Gwadar – Turbat – Hoshab (M-8)

Project

Gwadar – Turbat – Hoshab (M-8)

Location Balochistan
Estimated Cost (US $ Million) Rs. 13 Billion
Project Progress Update
  • Completed and Inaugurated